On April 9, 2015, MIGA issued a guarantee of $63 million covering an equity investment by Tata Power International Pte. Ltd. of Singapore in the Adjaristsqali Hydro Project in Georgia. The coverage
Georgia
Host Country
Georgia
Guarantee Amount
$63 million
Sector
Power
Approval Date
December 16, 2014
Project Status
Active

Project description

On April 9, 2015, MIGA issued a guarantee of $63 million covering an equity investment by Tata Power International Pte. Ltd. of Singapore in the Adjaristsqali Hydro Project in Georgia. The coverage is for a period of up to 15 years against the risks of transfer restriction, expropriation, war and civil disturbance, and breach of contract.

The project involves the construction and operation of the 187 megawatt Shuakhevi hydropower project, consisting of the 178 MW Shuakhevi plant and the nine megawatt Skhalta plant. It is part of the Adjaristsqali cascade of three run-of-the-river hydropower plants with a total planned installed capacity of 400 megawatts. The International Finance Corporation (IFC), the European Bank for Reconstruction and Development, and the Asian Development Bank are providing debt financing for the project.

The project will export power to Turkey through the 400 kV Akhalskhe-Borcka cross-border transmission line for nine months of the year, and sell domestically for three consecutive winter months for the first 10 years of operations. In order to connect to the state grid, a 220kV transmission line from the power station to the national grid is being built with financing from the World Bank.

With the support of the World Bank, the government of Georgia is pursuing two strategic objectives: ensuring continued reliable domestic energy supply for firms and homes and bolstering electricity production from hydropower plants to expand the regional electricity trade. The World Bank has helped extensively in developing market rules, network infrastructure, and financial solutions to leverage private investment in support of Georgia’s energy objectives. This project is expected to have a positive demonstration effect on other potential private investors into Georgia’s hydropower sector. The country has a large pipeline of hydro projects for which the Georgian government is actively seeking foreign participation.

MIGA’s support for this project is aligned with the Agency’s priority of supporting transformational projects.

Project ID
12315
Strategic Priority Area
Transformational Project
Guarantee Holder
Tata Power International Pte. Ltd.
Investor Country
Singapore
Environmental Category
A
Date SPG Disclosed
April 12, 2014
Board Approval Date
December 16, 2014
Project Type
Non-SIP
Fiscal Year
2015
Region
East Asia and Pacific (EAP)

Delivering Development with Transparency and Integrity

Need additional information? Reach out to request access.

Related Projects

Lobito-Luau Railway Corridor Project

Angola
Infrastructure
Proposed
The Project consists of the operation, management and maintenance of approx. 1,350 km of railway line, a brownfield infrastructure asset which crosses Angola from east to west, from the city of Luau at the border with the Democratic Republic of

Sembcorp Myingyan Power Company Limited

Myanmar
Power
Active
This summary covers equity and shareholder loan investments from Sembcorp Utilities Pte. Ltd. , a non-shareholder loan from commercial lenders Clifford Capital Pte. Ltd. , DBS Bank Ltd. (“

PT Perusahaan Listrik Negara (Persero)

Indonesia
Renewable Energy
Active

This summary covers a proposed investment by Citibank, N.A., Singapore Branch of the United States of America, DBS Bank Ltd. of Singapore, JPMorgan Chase Bank, National Association, Singapore Branch of the United States of America, KfW IPEX-Bank GmbH of Germany,