Infinity Benban Park Solar Energy S.A.E.
MIGA’s latest project is part of Egypt’s Feed-in-Tariff Round Two program, which consists of the design, development, construction, operation and maintenance of a greenfield solar IPP facility
solar panel field sunset
Host Country
Egypt, Arab Republic of
Guarantee Amount
$2.25 million
Sector
Power
Board Approval Date
September 20, 2017
Project Status
Not Active

On December 8, 2017, MIGA signed a contract in which it agreed to issue $2,247,244 in guarantees to ib vogt GmbH of Germany for its investments in Infinity Benban Park Solar Energy S.A.E.. The guarantees are issued for up to 15 years against the risks of Transfer Restriction and Inconvertibility, Expropriation, War and Civil Disturbance, and Breach of Contract.[i]

The project is part of Egypt’s Feed-in-Tariff Round Two program. It consists of the design, development, construction, operation and maintenance of a greenfield solar IPP facility with installed capacity of 50 MW located in the Benban solar PV park in the Aswan Governorate of Egypt. 

 

Environmental Categorization

The project is categorized as B under MIGA’s Policy on Environmental and Social Sustainability. Click here for the project’s Environmental and Social Review Summary.

 

Development Impact

Egypt needs additional power generation capacity to meet growing energy demands and support economic growth along with private sector development. Despite hydrocarbon production and significant new gas discoveries, Egypt is a net importer of fossil fuels, which account for over 90% of its power generation. The project will add generation capacity, diversify the power generation mix, increase self-sufficiency, and reduce dependence on fossil-fuel imports. The project will help protect Egypt’s economy from fluctuations in oil and gas prices, and reduce carbon emissions by producing emission-free power, in alignment with the goals of the Paris Agreement.

[i] The guarantee was cancelled on June 07, 2021.

Project ID
13961
Strategic Priority Area
Energy efficiency and climate change
Guarantee Holder
ib vogt GmbH
Investor Country
Germany
Environmental Category
B
Date SPG Disclosed
August 10, 2017
Board Approval Date
September 20, 2017
Project Type
Non-SIP
Fiscal Year
2018

Delivering Development with Transparency and Integrity

Need additional information? Reach out to request access.

Related Projects

KfW - Development Bank of Kazakhstan NHFO-SOE

Kazakhstan
Active

On September 29, 2026, MIGA issued a guarantee of US$190 million to KfW, representing 95 percent of a US$200 million non-revolving open credit facility, non-shareholder loan to the Development Bank of Kazakhstan JSC (DBK) in the Republic of Kazakhstan (“Kazakhstan”).

Development Bank of Kazakhstan NHFO-SOE

Kazakhstan
Infrastructure
Active

On June 30, 2026, MIGA issued two guarantees totaling US$998 million to cover SCB, J.P. Morgan, and CB’s loan to the Development Bank of Kazakhstan (DBK), providing coverage against the risk of non-honoring of financial obligations for a state-owned enterprise,

Trade Finance Guarantee Framework Agreement with Deutsche Bank

Multiple Countries
Trade Finance
Proposed

This summary is for a potential MIGA guarantee to be issued to Deutsche Bank AG (DB) to support a portfolio of trade transactions facilitated via State-Owned Banks and Central Banks (Obligors) in Emerging Markets and Developing Economies (EMDEs).