QMM 6th Generator
This summary covers an investment by QIT Madagascar Minerals Ltd of Bermuda for one of six generator sets within a power plant, as well as associated transmission facilities to supply power to the tow
Host Country
Madagascar
Guarantee Amount
$3.3 million
Sector
Infrastructure
Approval Date
October 23, 2008
Project Status
Not Active

Project Description

This summary covers an investment by QIT Madagascar Minerals Ltd of Bermuda for one of six generator sets within a power plant, as well as associated transmission facilities to supply power to the town of Fort Dauphin in Madagascar. The investors have applied for a MIGA guarantee of $3.3 million for a period of up to 10 years against the risk of breach of contract.

QIT Madagascar Minerals S.A. (QMM) is 80 percent owned by Rio Tinto through QIT Madagascar Minerals Ltd. QMM is developing an Ilmenite mine with associated port facilities in Madagascar. Power supplied by the state-owned utility, JIRAMA, for QMM’s mining operations is insufficient. Therefore, QMM is building its own power plant and installing five generators that will supply power for its mining operations to the Port of Ehoala.

QMM is also installing and operating an additional generator (the sixth) in order to address power shortages in the town of Fort Dauphin. Electricity generated will be sold to JIRAMA under a 10-year power purchase agreement signed with QMM. 

This project falls within the scope of a larger World Bank-supported project—the Integrated Growth Poles Project for Madagascar. Click here for documents related to the project.

Environmental Categorization

The project is a Category B under MIGA’s environmental review procedures.

Development Impact

Fort Dauphin falls within one of Madagascar’s poorest areas with GDP per capita of $180. Access to electricity by Fort Dauphin’s estimated 360,000 inhabitants is scarce and sporadic (estimated at 31 percent). Load shedding and electricity shortfalls are having an adverse effect on the local economy. The project is expected to provide sufficient electricity to meet the current needs of Fort Dauphin and contribute significantly to the area’s development. In general, the project is expected to contribute towards increasing power supply in the country reliably and in a cost-effective manner.

Project ID
7384
Investor Country
Bermuda
Environmental Category
B
Date SPG Disclosed
September 21, 2008
Target Board Decision Date
October 23, 2008
Project Type
Non-SIP
Fiscal Year
2009

Delivering Development with Transparency and Integrity

Need additional information? Reach out to request access.

Related Projects

Azito Thermal Power Plant and Expansion

Côte d'Ivoire
Power
Active
In December 2012, MIGA issued guarantees totaling $116. 1 million covering an investment by Globeleq Holdings (Azito) Limited of Bermuda in the Azito Thermal Power Plant in Côte d’Ivoire. Th

Azito Thermal Power Plant and Expansion

Côte d'Ivoire
Power
Active
This summary covers an equity investment and/or shareholder loan by Globeleq Holdings (Azito) Limited of Bermuda for the Azito Thermal Power Plant in Côte d’Ivoire. The investor has applied

Azito Thermal Power Plant and Expansion

Côte d'Ivoire
Power
Active
The Environmental and Social Review Summary prepared by the International Finance Corporation (IFC) for their investment in the project